In our experience, a bathroom refit takes anywhere from about a week to about a month of work on site. A like-for-like swap -- new suite in the same positions, with little retiling -- can be done in around a week. A full refit with new tiling throughout usually takes two to three weeks. Moving the toilet or shower, building a wet room or adding underfloor heating pushes it towards a month.
Those are days on site. Before them come the weeks spent planning, ordering products and getting into an installer's diary; after them, a few days before everything has cured enough for full use. Here's where the time goes, and how to stop it stretching.
Bathroom refit timescales at a glance
| Job | Working days on site | Roughly | What drives it |
|---|---|---|---|
| Retile only | 3-5 | Under a week | Room size, tile format, how much comes off |
| Like-for-like refit | 5-7 | About a week | Suite stays put, little new pipework |
| Full refit with new tiling | 10-15 | Two to three weeks | Full strip-out, new pipework and electrics, tanking, tiling throughout |
| Layout change, wet room or underfloor heating | 15-20+ | Three weeks to a month | Moving waste runs, building falls, extra floor work |
"Working days" means days the team is on site, normally Monday to Friday, so ten working days is two calendar weeks. A lot of the estimates you'll find online mix the two, which is one reason the figures vary so much.
The stages of a bathroom refit, in order
Every full refit follows the same basic order. The timings below are for a typical family bathroom with new tiling throughout.
1. Strip-out (1-2 days)
The water is isolated and everything comes out: suite, tiles and often the old plasterboard. It's the noisiest, dustiest stage, and the one where surprises turn up -- a rotten joist under a toilet that's been leaking for years, old pipework, walls that crumble once the tiles are off. In older Surrey homes we expect to find something; the question is how much.
2. First fix: plumbing and electrics (2-3 days)
New supply and waste pipes are run to wherever the shower, basin, bath and toilet will sit, along with cables for lighting, the extractor fan, shaver point and heated towel rail. All of it disappears behind the walls, so this is the point where everything has to be decided: valve heights, niche positions, where the towel rail goes. Changing your mind once the walls are boarded costs days.
3. Boarding, floor prep and tanking (1-3 days)
Walls are boarded with moisture-resistant or cement-based board, floors are overboarded or levelled, and the shower and bath areas are tanked with a waterproof membrane that sits under the tiles. Liquid tanking goes on in coats that need to dry between applications, so this stage can't be squeezed into an afternoon. Depending on the tray and bath, they're often fitted now so the tiles can be finished down onto them.
4. Tiling and grouting (3-6 days)
Usually the longest single stage. Walls and floor are tiled, the adhesive is left to set, then everything is grouted. Large-format porcelain, patterned layouts and natural stone all take longer than standard wall tiles, and a room tiled floor to ceiling takes longer than one tiled to half height.
5. Second fix (2-3 days)
The suite, taps, shower valve trims, screen, furniture, mirror, lights and towel rail go in and are connected. This is when the room suddenly looks finished, but there's still a day's work left.
6. Sealing, testing and handover (1 day)
Joints are siliconed, everything is run and checked for leaks, the room is cleaned, and we walk you through it. Any notifiable electrical work should come with its certificate at this point.
Waiting times you can't rush
Several stages involve materials that need time to dry or cure, and rushing them is the usual cause of cracked grout, split silicone and failed tanking. Exact times depend on the product and how warm and well ventilated the room is -- the manufacturer's data sheet always wins -- but these are typical:
| Material | Typical wait | Before |
|---|---|---|
| Liquid tanking | A few hours between coats, often overnight before tiling | Tiling |
| Tile adhesive | Around 24 hours (rapid-set: a few hours) | Grouting |
| Cement grout | 24-48 hours for light use; around 3 days before regular showering | Using the shower |
| Sanitary silicone | Around 24 hours | Getting it wet |
| New plaster skim | Several days to a week or more | Painting |
| Screed over wet underfloor heating | Weeks rather than days | Tiling and running the heating |
For example, Mapei advises waiting 3 days before using a shower grouted with one of its ready-mixed grouts, and longer in cold or humid conditions. Steam showers need much longer again. Electric underfloor heating mats, by contrast, sit in a thin layer of levelling compound and add only a day or so.
What makes a bathroom refit take longer
Hidden problems. Rotten boards or joists from old leaks, ageing pipework and walls that need replastering only show themselves once the room is stripped. Period homes are where we see this most, and it's why a good estimate is honest about what can't be known until the tiles are off.
Moving the toilet. A toilet has to connect to the soil pipe with a steady fall, so moving it more than a short distance can mean lifting more floor or rerouting the waste. Showers and basins are far more flexible.
Product lead times. Made-to-order vanity units, special-order tiles and some brassware can take weeks to arrive. A part that turns up damaged or wrong mid-job stalls everything behind it.
Changing your mind mid-job. Moving a niche, valve or light after the walls are boarded means undoing finished work.
Wet rooms on timber floors. Building the fall to the drain into a suspended timber floor means extra floor work before any tanking or tiling can start. See can you have a wet room upstairs? for what's involved.
Permissions. A listed building can need listed building consent before work starts, and a flat may need the freeholder's consent under the lease. Neither adds days on site, but both can push back the start date by weeks, so check early. See building regs and permission for a new bathroom.
How far ahead should you book?
Good bathroom fitters are rarely free next week, so ask for a likely start date when you get your quote rather than after you've accepted it.
The other lead time is products. We prefer to have everything on site and checked before the old bathroom comes out. A refit that stops halfway while you wait for a shower tray is the most frustrating kind of delay, because you're without a bathroom the whole time.
Living without a bathroom during the refit
You'll be without that room for the whole job. If it's your only bathroom, plan for it before day one:
- The toilet. Ask about keeping it connected for as long as the work allows. We'll always talk this through at the home visit.
- Showers. A gym, family or a friend nearby -- for a two- to three-week job, it's worth arranging in advance.
- Water. The supply is off for short periods during the strip-out and first fix. You'll get notice.
- Dust. The strip-out is the messy part. Expect the room to be sealed off and floors protected along the route in from the front door.
With a second bathroom or a downstairs toilet, the disruption is far easier to live with.
How to keep your refit on schedule
- Make every decision before the start date: layout, tiles, grout colour, valve and niche positions, towel rail and lighting.
- Have products delivered before the strip-out, and check them as soon as they arrive.
- Ask for a written, stage-by-stage schedule with your estimate -- and the other questions to ask a bathroom fitter.
- Agree where the skip and vans will go, and keep that space clear.
- Use one team for every trade if you can. Each handover between separate plumbers, electricians and tilers is a chance for a day or two to slip, which is why we handle the whole refurbishment ourselves.
Bathroom refit timescale FAQs
Can a full bathroom refit really be done in a week?
Only if it's close to like-for-like: the suite stays where it is, little pipework changes and tiling is limited. A full refit with new tiling takes longer, because tanking, adhesive and grout all need time to cure. The Federation of Master Builders puts a standard renovation at two to four weeks.
Is it quicker if I strip out the old bathroom myself?
Rarely by much. Strip-out takes one to two days, and doing it yourself risks damaging pipes, floors or walls that then need repairing. We also use the strip-out to check what's under the floor and behind the walls before committing to the next stages, which is harder in a room someone else has cleared.
Can the work be done over weekends or in stages?
It's possible, but it stretches the job: each stage has to stop, be protected and restart, and you're without a working bathroom for longer overall. A continuous block of working days is almost always quicker and less disruptive. If you need the work staged, raise it when you get your quote.
Planning a refit? We'll visit, measure up and give you a written, stage-by-stage schedule alongside your estimate, so you know before you book how long you'll be without your bathroom. See how our bathroom refurbishments work, or request a free home visit.